The Development of an European Digital Portfolio
for the Evaluation of  Educators

?

 

???
Education and Culture

?
    TRAINING COURSE ? PROJECT OUTCOMES ?? PROJECT ACTIVITIES

 

Work Plan

Project:

 

Stage in life of project

Outputs:
By the end of this stage we will have achieved / produced

Activities
leading to this output

 

Activity to be started by this date

and completed by this date

Partners / Persons involved

Time input

(person / days or

person / months)

1. ANALYSIS

 

 

-Website

 

1.0 Report on meeting results (criteria for the analyses)

 

 

1.1     Comparative study to the design, structure and general practice of appraisal systems in Europe

 

1.2. Description and listing of the various forms they may take

1.3. Analysis of each country’s system in terms of its weaknesses, strengths, problems, solutions and results

1.4. Analysis, which software educators use regularly

1.5. Description and listing of the content of the information tool.

-Open a Website branch (linking with PG institutions)

1.0 Meeting 1 in NL

(project management)

Seminar to present by each country its current appraisal system

 

1.1     Analysis of the existing appraisal systems in particular in the countries of the project partners

 

 

1.2/3 Analysis of tools used for the evaluation/assessment of educators in particular Portfolios and Digital Portfolios of achievements/competencies with a particular focus on the countries of the project partners

 

1.4. Analysing how frequent educators use specific software

 

 

1.5. Describing and listing the content of the Information Tool.

 

 

1.0 NL meeting:

Arrival: Wednesday 23.10.2002

Departure: Sunday 27.10.2002

 

1.1  Start at time of approval and complete before the second meeting

 

 

 

 

1.2/3 Start after meeting 1 and complete by meeting 2

 

 

 

 

 

 

1.4     Start during meeting 1 and complete by meeting 2

 

 

1.5     Start during meeting 1 and complete by meeting 2

 

-CY

 

1.0     CY+PG+RG

       +TEG+CNS

 

 

 

 

1.1.  CY +PG+TEG+CNS

 

 

 

 

1.2/3.   CY +PG+RG+

            TEG+GD+CNS

 

 

 

 

 

 

1.4     CY+PG+RG+CNS

 

 

 

1.5     CY+PG+RG+TEG

       +GD+CNS

 

Partners personel:

312 person days

 

Comparative study:15 days

 

External evaluation : 4 days

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

2. DESIGN-  PRODUCTION

 

2.0 Meeting results

     Criteria for sampling of the implementation group

 

2.1 Requirements for Digital Portfolio

 

 

2.2 Technology requirements

 

 

2.3 First year report

 

 

2.4 Draft Digital Portfolio and Draft of Digital Manual

Post-card for dissemination

 

2.5 Meeting results

One educator from each partner education area/level trained as Information tool and Digital Portfolio user evaluator

 

2.6 Trial and correction report

 

2.7. First prototype of English version of Digital Portfolio

 

2.8 Translated D-Portfolios

 

2.0. Meeting 2 in CY

 

 

 

2.1.  Analysis and listing of the

 requirements for the development of the Digital Portfolio

 

2.2.    Comparative assessment and choice of technologies required for the development of the Digital Portfolio

2.3     Collection of documents for

       the first year report

 

2.4     Design and implementation of the digital portfolio and the information tool. Design of a post-card for Dissemination

2.5     Meeting 3 in CY

Evaluation training meeting for the pilot group

  

     

2.6     Technical Piloting Evaluation of the digital portfolio (English version)  and the Information tool.

2.7     Implementation of correction report

 

 

 

2.8     Translation in the languages of the partner countries

 

 

2.0 January-Feb 2003 Cyprus

Arrival Wednesday, 29 /1/ 2003

Departure: 3 February 2003

 

2.1 Start during meeting 2 and complete within meeting 2

 

 

2.2. Start on January 2003 and completed by 31 May 2003

 

 

2.3 Start during meeting 1 and completed by August 2003

 

2.4 Start on 1st June 2003 and completed by 31 August 2003

 

 

2.5. Cyprus

Arrival : Th., 9 October, 2003

Departure: 13 October, 2003

 

 

2.6. Trial starts after meeting 3 and completed by 30 November 2003, report completed by 31 December

 

2.7. Final changes start on 1st January 2004 and completed by 31 January 2004 

 

2.8. Starts on 1st September 2003 and is completed by 15 February 2004

 

2.0     CY+PG+RG+CNS

       +TEG

 

 

2.1. CY+PG+RG

       +TEG+GD+CNS

 

 

2.2. CY+PG+RG+

       TEG+CNS

 

 

2.3 CY+PG+CNS

 

 

2.4. CY+PG+RG+TEG+

       GD+CNS

 

 

2.5. CY+PG+RG+TEG+

      CNS + Pilot Group

 

 

 

2.6. CY+ PG+TEG+

       CNS+ Pilot Group

 

 

 

2.7 CY+RG+TEG+CNS

 

 

 

2.8 CY+PG+RG+

      TEG+CNS

Partner personnel :

360

person days

 

External evaluation : 8 days

 

 

Translation of D-P into other languages : 48

 

Technical development : 80 days

3.  IMPLEMENTATION-

         EVALUATION

3.0. Report on Meeting results

 

3.1. Design of a training course for the implementation

group in each country .

 

3.2 Trained educators to be able to develop their Digital Portfolio

3.3. Evaluation tool

 

3.4 Implementation with selected group (10 educators selected by each partner, a  sample over the different type of educators)

3.5 Evaluation report on implementation

 

3.6 Second year report

 

 

 

3.7. Report on Meeting results

 

3.8 Final improved version in all languages of the partner countries

 

 

3.9 In-Service Training Course delivery plan (Comenius 2.2 proposal)

3.0 Meeting 4 in ES

 

 

3.1. Training course for the implementation groups in each country separately

 

 

3.2 Training of educators

      

 

3.3 Design of the evaluation to be used during the implementation

3.4. Implementation with a sample in each partner country

 

 

 

3.5. Evaluation of implementation

 

 

3.6 Collection of documentation for the second year report

 

 

3.7. Meeting 5 in AT

 

 

3.8. Development of the final improved version of the Digital Portfolio

 

 

 

3.9. Design of In-Service training course as a means of future dissemination

3.0. Meeting 4,

January 2004 - Spain

Arrival: Wednesday 14, JAN

Departure: Sunday 18, JAN

 

3.1 Starts during meeting 4 and completed during meeting 4

 

3.2 Starts after meeting 4 and completed by 30 March 2004

 

3.3 Starts during meeting 4 and completed by 30 March 2004

3.4 Starts on 1st April 2004 and completed by 30 June 2004

 

 

 

3.5 The evaluation of implementation will begin during the training course and will be completed by  July 2004

3.6 Starts during the 3rd meeting and completed by 31st August 2004

3.7  Meeting 5: Austria(upper)

October 2004

Arrival: Wednesday 20 October 2004

Departure: Sunday 24 October 2004

3.8 Start during meeting 5 and completed by the 31 December 2004

3.9 Start during meeting 5 and completed during meeting 5

 

3.0    CY+PG+RG+

       TEG+CNS

 

 

 

3.1 CY+PG+RG+TEG

 

 

3.2 CY+PG+TEG+CNS

 

 

3.3 CY+PG+RG+

      TEG+CNS

3.4 CY+PG+RG+

      TEG+CNS

 

 

 

3.5 CY+PG+RG+CNS

 

 

3.6. CY+PG+CNS

 

 

 

3.1    CY+PG+RG+

        TEG+CNS

 

3.2    CY+PG+RG+

       TEG+CNS

 

 

 

 

3.9 CY+PG+RG+TEG

Partner personnel :

350

person days

 

External evaluation : 8 days

 

Technical Piloting evaluation : 150 days

 

4         DISSEMINATION-

FINAL  PROJECT EVALUATION

 

4.0 Report on Meeting results

 

 

4.1. Digital Portfolio on a CD-ROM / Web-site with cross-carrier support in the languages of the partner countries

 

4.2. Dissemination plan, web advertisement, press conference

 

4.3. Exploitation strategy (Network of users and sustainability provision)

 

4.4 Press conference

 

 

4.5. Final Evaluation report

 

 

4.6 Final Report

 

4.0. Meeting 6 in CY

 

 

 

4.1. The Digital Portfolio will be made available on a CD or a downloadable file through the project web

 

 

4.2. Dissemination of results

 

 

 

4.3.Exploitation planning

 

 

 

4.4     Planning of an European press conference

 

4.5. Evaluation of the project

 

 

4.6 Collection of documents for the final report

 

 

 

4.0 February 2005 - Cyprus

Arrival: TBA

Departure: TBA

4.1 Start 1st January 2005 and complete by 15 February 2005

 

 

 

4.2 Start during meeting 6 and completed during meeting 6

 

 

4.3 Start during meeting 6 and completed by 30 April 2005

 

4.4 Time to be arranged. Not later than 30 May 2005

 

4.5 Start during meeting 6 and completed by 30 May 2005

 

4.6 Start during meeting 5 and completed by August 2005

 

 

4.0     CY+PG+RG+

       TEG+CNS

 

4.1 CY+PG+TEG+CNS

 

 

 

 

4.2 CY+PG

 

 

 

4.3 CY+PG+CNS

 

 

 

4.4 CY+PG

 

 

4.5 CY+PG+CNS

 

 

 

4.6 CY+PG+CNS

 

 

Partner personnel :

280

person days

 

External evaluation : 4 days